Background Image
Table of Contents Table of Contents
Previous Page  44 / 52 Next Page
Information
Show Menu
Previous Page 44 / 52 Next Page
Page Background

44

The tower’s blend of design and technology sets the

pace in this vibrant commercial district. Surrounded by

water features and natural landscaping, the iconic glass

structure provides a comfortable working environment

for its tenants.

Progressive technology

Metrotower III is the first project in British Columbia to

implement the KONE Polaris

Destination Control System

(DCS). Relying on smart technology to detect calls and

passenger information over a period of time, it anticipates

traffic, and adapts elevator operations accordingly.

Nine high-speed KONE elevators – 5 meters per second

– deliver smooth and reliable transportation from the

underground parking to the lobby. The energy-efficient

KONE EcoSystem MR

elevators reduce total energy

consumption – car lighting and electrification – helping

the building meet LEED certification requirements plus

decreasing the building owner’s on-going operational

costs.

METROTOWER III – VANCOUVER, CANADA

Built for tomorrow

Metrotown Properties – a dazzling commercial development in Vancouver – is reinventing Canada’s urban

experience. The complex is flanked by high-rise developments and Metrotower III, a 29-floor LEED®-certified

Platinum “AAA” Class office building, is at the heart of it all.

Solid partnership

The developer’s construction schedule included no margin

for error. Completion of the commercial-use elevators

was carefully timed to coincide with the removal of a

construction skiplift. “The contractor had several critical

milestones on this project,” explains

Dennis Viehweg

,

District Manager for KONE in Western Canada. “We

wanted to make sure that we met the schedule and that

installation proceeded without problems. If we failed, our

customer would miss their occupancy dates.”

KONE Major Projects worked closely with Developer Ivanhoe

Cambridge Inc. and Contractor Ledcor Construction Ltd.

to ensure an on-time delivery. A detailed traffic analysis and

planning process provided clarity early in the design phase.

“We helped our customers to understand the project’s

challenges and complexities before the work started,”

Viehweg says, “and that allowed us to meet the milestones

they set.”

A dedicated on-site project manager guided the project,

tracking schedules and providing constant communication.

“The intensity of that singular focus ensured that everyone

was kept informed,” Viehweg adds.

© Barbara Cameron